EXECUTIVE SUMMARY:
Our objective was to determine whether Thomas Jefferson University (the University) cost transfers to federally funded grants were documented in accordance with Federal requirements. The University generally documented cost transfers to federally funded grants in accordance with Federal requirements. Through documentation and explanation, the University was able to justify all the transfers. We have no recommendations to report.